Project Details
The development comprised the folllowing:
- Construction of a new 10 storey apartment building including carparking and ground floor commercial premises
- Retention of existing heritage facade
Challenge Faced / Engineering Problem Solved:
- Convict mine workings were discovered during grout injection of piles
- Variable founding depths due to convict workings required detailed pile assessment with geotechnical engineers
- Provision for temporary support systems to heritage façade whilst constructing new concrete frame and suspended floors to provide new lateral façade support
Safe Strong Stable Solution
Construction systems used included:
- Building supported on reinforced concrete grout injected piles
- Reinforced concrete pile caps, ground slabs, footings and tie beams
- Conventionally reinforced concrete columns, shear walls, cores and stairs
- Post-tension suspended concrete systems
- Heritage façade retention using existing supports and new structure
- Precast concrete loadbearing cladding panels
Engineering Design Services / Reviews
- Earthquake and wind modelling, analysis and design using conventional reinforced concrete shear wall and core systems
- Staged façade support design methods used
- Footing and pile cap foundation analysis and design
- Reinforced concrete column and wall analysis and engineering design
- Suspended concrete upper level slab and beam designs using post tension systems
- Structural steel roof rafters, purlins and awning framing analysis and engineering design
Project Type
Existing Building Demolition
Façade Retention
New Building Construction
Engineering Type
Structural
Construction Phase Services
Project Stages
- Site Investigation and Assessment of founding conditions and convict mine workings discovered
- Assessment of existing heritage façade and retention methods required
- Structural Engineering Design and Documentation
- Design Workshops and Project Meetings
- Design Coordination with all Consultants, Client and Principal Contractor
- Safety in Design / Environmental Considerations
- Construction Phase Services – Site Inspections, RFIs, Shop Drawing Reviews
Newcastle Ocean Baths
Client | Newcastle City Council
Dyke Point Refurbishment
Client | Newcastle Port Corporation
123 Scott Street Apartments
Client | Boardcross Australia Pty Ltd
Grand Central Apartments
Client | Pacific Lifestyle Projects Pty Ltd
Fred Ash
Building
Client | Newcastle City Council